Elite Electrical Contractors
Demo mode

Automations

The chain that turns a verbal direction on site into money in the bank. Each step happens without anybody remembering to do it.

5 of 6 running

The chain

Site instruction
Logged on site, photo attached
AI drafts variation
Priced from the rate schedule
Submitted to builder
With the instruction attached
Approved
Revised contract sum updated
Auto-added to next claim
Before the reference date
Paid
Reconciled to the payment schedule

The chain breaks in the same place every time: someone gives a verbal instruction, the electrician does the work, and no variation is ever raised. Step two is where the money is saved.

Site instruction → variation draft

When A site instruction is logged on site. Then A draft variation is created against the job within 60 seconds, priced from the rate schedule and attached to the instruction.

Runs this month
6
Value covered
A$12,150

Variation approved → added to next claim

When A head contractor approves a variation. Then The variation is added to the next progress claim for that job and flagged in the claim build.

Runs this month
9
Value covered
A$127,400

Reference date approaching → claim reminder

When 5 days before a job's contractual reference date. Then A reminder goes to the contracts administrator with the draft claim, stat dec and backup pack ready to review.

Runs this month
6
Value covered
A$942,000

DLP ends → retention release request

When A job reaches PC or its Defects Liability Period ends. Then A retention release request is drafted to the head contractor with the contract clause and dates cited.

Runs this month
3
Value covered
A$53,000

Claim short-paid → payment schedule review

When A payment schedule comes back below the amount claimed. Then A review task is created with the shortfall, the reasons given, and the deadline to lodge an adjudication application.

Runs this month
5
Value covered
A$64,600

RFI unanswered 7 days → escalation

When An RFI has been open for 7 days with no response. Then An escalation email is drafted to the builder's project manager and the delay is noted in the site diary for any future EOT.

Runs this month
0
Value covered

What is switched off

RFI escalation is off. Four RFIs are currently overdue, the oldest open 43 days on Northbridge Health — and the delay claim on Marsden Industrial rests on an RFI that went 19 days without an answer. Turning it on drafts the escalation email and writes the delay into the site diary automatically.