Elite Electrical Contractors
Demo mode

RFIs

Questions to the builder and consultants. An RFI left unanswered is a delay claim waiting to happen — and the site diary entry that proves it.

RFIs raised
12
Across 6 jobs
Overdue
4
Open more than 14 days
Open
4
Longest open
43
RFI-041 · Northbridge Health
With cost impact
7
Each one may become a variation
RFIJobRaisedQuestionDirected toDays openImpactStatus
RFI-041Northbridge Health Precinct Stage 216 Jun 2026Confirm the earthing arrangement for the imaging suite — architectural and services drawings conflict.Daniel ReyesStanton Reid Constructions43CostOverdue
RFI-044Lidcombe Distribution Centre Stage 122 Jun 2026Which authority supply arrangement applies — is the substation lease signed?Ruth SalinasAshfield Bell37TimeOverdue
RFI-046Meriton Logistics Hub Warehouse 429 Jun 2026Confirm lux levels required in the racking aisles following the tenant layout change.Tom WhelanKembla Construction Group30CostOverdue
RFI-048Waverton Public School Upgrade9 Jul 2026Is the fire engineer's exit signage report the current revision for pricing?Ben LatimerDelmore Projects20CostOverdue
RFI-050Northbridge Health Precinct Stage 217 Jul 2026Provide the approved switchboard schedule for Level 3 after the DB-3.2 relocation.Daniel ReyesStanton Reid Constructions12CostOpen
RFI-045Waverton Public School Upgrade24 Jun 2026Provide the COLA lighting control zoning diagram.Ben LatimerDelmore Projects11NoneAnswered
RFI-043Parkline Retail Fitout18 Jun 2026Confirm the shopfront signage supply point locations.Nadia KovacHarrow Built9CostAnswered
RFI-051Marsden Industrial Estate Building C21 Jul 2026Confirm the pole footing detail after the civil re-set out of the car park.Daniel ReyesStanton Reid Constructions8TimeOpen
RFI-052Parkline Retail Fitout23 Jul 2026Confirm tenancy metering responsibility — landlord or tenant?Nadia KovacHarrow Built6CostOpen
RFI-047Meriton Logistics Hub Warehouse 42 Jul 2026Confirm the sprinkler pump room control interface protocol.Tom WhelanKembla Construction Group6CostAnswered
RFI-049Riverside Tower Levels 12–1814 Jul 2026Confirm which party holds the tenancy metering NMI registrations post-PC.Ruth SalinasAshfield Bell4NoneAnswered
RFI-053Lidcombe Distribution Centre Stage 126 Jul 2026Advise the final camera positions for the perimeter fence cabling.Ruth SalinasAshfield Bell3NoneOpen