RFIs
Questions to the builder and consultants. An RFI left unanswered is a delay claim waiting to happen — and the site diary entry that proves it.
RFIs raised
12
Across 6 jobs
Overdue
4
Open more than 14 days
Open
4
Longest open
43
RFI-041 · Northbridge Health
With cost impact
7
Each one may become a variation
| RFI▲ | Job▲ | Raised▲ | Question▲ | Directed to▲ | Days open▼ | Impact▲ | Status▲ | |
|---|---|---|---|---|---|---|---|---|
| RFI-041 | Northbridge Health Precinct Stage 2 | 16 Jun 2026 | Confirm the earthing arrangement for the imaging suite — architectural and services drawings conflict. | Daniel ReyesStanton Reid Constructions | 43 | Cost | Overdue | |
| RFI-044 | Lidcombe Distribution Centre Stage 1 | 22 Jun 2026 | Which authority supply arrangement applies — is the substation lease signed? | Ruth SalinasAshfield Bell | 37 | Time | Overdue | |
| RFI-046 | Meriton Logistics Hub Warehouse 4 | 29 Jun 2026 | Confirm lux levels required in the racking aisles following the tenant layout change. | Tom WhelanKembla Construction Group | 30 | Cost | Overdue | |
| RFI-048 | Waverton Public School Upgrade | 9 Jul 2026 | Is the fire engineer's exit signage report the current revision for pricing? | Ben LatimerDelmore Projects | 20 | Cost | Overdue | |
| RFI-050 | Northbridge Health Precinct Stage 2 | 17 Jul 2026 | Provide the approved switchboard schedule for Level 3 after the DB-3.2 relocation. | Daniel ReyesStanton Reid Constructions | 12 | Cost | Open | |
| RFI-045 | Waverton Public School Upgrade | 24 Jun 2026 | Provide the COLA lighting control zoning diagram. | Ben LatimerDelmore Projects | 11 | None | Answered | |
| RFI-043 | Parkline Retail Fitout | 18 Jun 2026 | Confirm the shopfront signage supply point locations. | Nadia KovacHarrow Built | 9 | Cost | Answered | |
| RFI-051 | Marsden Industrial Estate Building C | 21 Jul 2026 | Confirm the pole footing detail after the civil re-set out of the car park. | Daniel ReyesStanton Reid Constructions | 8 | Time | Open | |
| RFI-052 | Parkline Retail Fitout | 23 Jul 2026 | Confirm tenancy metering responsibility — landlord or tenant? | Nadia KovacHarrow Built | 6 | Cost | Open | |
| RFI-047 | Meriton Logistics Hub Warehouse 4 | 2 Jul 2026 | Confirm the sprinkler pump room control interface protocol. | Tom WhelanKembla Construction Group | 6 | Cost | Answered | |
| RFI-049 | Riverside Tower Levels 12–18 | 14 Jul 2026 | Confirm which party holds the tenancy metering NMI registrations post-PC. | Ruth SalinasAshfield Bell | 4 | None | Answered | |
| RFI-053 | Lidcombe Distribution Centre Stage 1 | 26 Jul 2026 | Advise the final camera positions for the perimeter fence cabling. | Ruth SalinasAshfield Bell | 3 | None | Open |