Lidcombe Distribution Centre Stage 1
KE-2408 · Ashfield Bell · Principal: Ashvale Logistics REIT · 17 Vaughan Street, Lidcombe NSW
On site
A$30,500 of approved variations on this job has never been invoiced
2 variations · add them to the next claim to Ashfield Bell
Contract sum
A$2,240,000
Variations approved
+A$106,700
Revised contract sum
A$2,346,700
Claimed to date
A$388,000
Outstanding
A$1,958,700
Revised sum less claimed
Unbilled variations
A$30,500
Retention held
A$38,800
5% of contract sum
Reference date
30th of each month
20 days from reference date
Progress21% complete · 17% claimed
Programme
Practical Completion
26 Jun 2027
Defects Liability Period ends
26 Jun 2028
12 months from PC
50% retention release
26 Jun 2027
Final retention release
26 Jun 2028
Head contractor
Builder
Ashfield Bell
Contact
Ruth Salinas
Contracts Administrator · rsalinas@ashfieldbell.com.au
Average days to pay
29 days
20 days from reference date
Short-payment rate
0%
Our team
Contracts administrator
Priya Nadeau
Project manager
Owen Brady
Foreman
Marcus Hale