Riverside Tower Levels 12–18

KE-2312 · Ashfield Bell · Principal: Riverside Corporate Trust · 300 Riverside Quay, Parramatta NSW

Defects Liability
A$12,800 of approved variations on this job has never been invoiced
1 variations · add them to the next claim to Ashfield Bell
Contract sum
A$840,000
Variations approved
+A$37,400
Revised contract sum
A$877,400
Claimed to date
A$864,600
Outstanding
A$12,800
Revised sum less claimed
Unbilled variations
A$12,800
Retention held
A$42,000
5% of contract sum
Reference date
30th of each month
20 days from reference date
Progress100% complete · 99% claimed

Programme

Practical Completion
15 Apr 2026
Defects Liability Period ends
15 Apr 2027
12 months from PC
50% retention release
15 Jul 2026
Final retention release
15 Apr 2027

Head contractor

Builder
Ashfield Bell
Contact
Ruth Salinas
Contracts Administrator · rsalinas@ashfieldbell.com.au
Average days to pay
29 days
20 days from reference date
Short-payment rate
0%

Our team

Contracts administrator
Priya Nadeau
Project manager
Priya Nadeau
Foreman
Marcus Hale
Sector
Commercial