Elite Electrical Contractors
Demo mode
← All jobs

Marsden Industrial Estate Building C

KE-2405 · Stanton Reid Constructions · Principal: Marsden Estate Holdings · 8 Marsden Park Drive, Marsden Park NSW

On site
A$14,700 of approved variations on this job has never been invoiced
1 variations · add them to the next claim to Stanton Reid Constructions
Contract sum
A$1,375,000
Variations approved
+A$31,100
Revised contract sum
A$1,406,100
Claimed to date
A$323,000
Outstanding
A$1,083,100
Revised sum less claimed
Unbilled variations
A$14,700
Retention held
A$32,300
5% of contract sum
Reference date
25th of each month
30 days from reference date
Progress31% complete · 23% claimed

Programme

Practical Completion
14 Nov 2026
Defects Liability Period ends
14 Nov 2027
12 months from PC
50% retention release
14 Nov 2026
Final retention release
14 Nov 2027

Head contractor

Builder
Stanton Reid Constructions
Contact
Daniel Reyes
Site Manager · d.reyes@stantonreid.com.au
Average days to pay
68 days
30 days from reference date
Short-payment rate
80%

Our team

Contracts administrator
Priya Nadeau
Project manager
Priya Nadeau
Foreman
Marcus Hale
Sector
Industrial